The adjuster who decides what gets paid on a water loss was not in the house. They read a file, often weeks after the equipment came out, with one question per line item: what shows this was necessary and happened? A file that answers it gets paid. One that asks for your word gets a phone call or a cut.

This checklist is organized by phase, because that is when each record is made. Each item carries the reason it matters to the claim, which is the part worth remembering: it tells a technician what to do when something comes up that the list did not anticipate.

First contact and intake

  • Date and time of loss, as reported. Time sitting shapes the category under ANSI/IICRC S500, which recognizes that clean water can degrade with time, and it starts the clock the drying timeline is judged against.
  • Date and time of the call, and who took it. Fixes response time and separates what existed before the call from anything after.
  • Source of water, as described. A supply line, a roof leak and a sewer backup lead to different categories and scopes. Record what the customer said and, later, what you found. Not an opinion on coverage.
  • Who reported it and their relationship to the property. Who was in a position to know what, and who can authorize work.
  • Authorization to proceed and the signed work authorization. Name, signature, date, time and the services authorized. Work done before authorization is the easiest charge to refuse, so the signature comes before the first air mover.
  • Claim number and adjuster contact, once assigned, with the date of your first conversation.

First visit

The first visit sets the baseline. Every later reading, equipment decision and demolition line is measured against what you record today.

  • Cause and origin photos. The source, the path the water took and how far it reached, shot before anything is moved. They tie the damage to a specific event and place.
  • Category and class per ANSI/IICRC S500, with the reasoning. Category describes contamination, from a sanitary source through grossly contaminated water; class describes how much wet, porous material is in the space and how hard it is to dry. Write both down with what you saw and measured. A determination with no reasoning reads as an opinion and gets challenged as one.
  • Pre-existing conditions. Old staining, previous repairs, deferred maintenance, growth that predates the loss. Photograph and note each one, so it stays out of the claim and your scope.
  • Moisture map of affected and unaffected areas. Room by room, material by material: the reading, the meter and mode, the point marked on the plan. The map shows the boundary of the loss, and the boundary is the scope.
  • Dry standard readings from unaffected materials. The moisture content of the same material where the water did not reach, one per material you will dry. The drying goal is set from it; without it, dry has no definition in the file.
  • Floor plan with dimensions and affected areas marked. Dimensions and ceiling height give the footage behind the equipment calculation; the marked area is the scope in one picture.
  • Contents affected. Moved, blocked and padded, set aside for the adjuster or discarded, with photos of anything discarded before it left the building.
  • Safety hazards. Electrical exposure, structural concerns, contaminated water, suspect materials in older buildings. Record the hazard, the control, and any work it prevented.
  • Initial equipment calculation and placement. Air mover and dehumidifier counts with the inputs behind them: square footage, class, cubic footage, unit capacity. Mark each unit on the plan with its asset number.

Daily monitoring

This is where most files fail, and where most of the money is. Equipment is billed by the day, and each billed day needs a record showing the unit was there, running and still needed. One missing day breaks the chain for every unit.

  • Psychrometric readings at four points. Temperature, relative humidity, grains per pound and dew point: outside, in an unaffected area, in the affected area and at the outlet of each dehumidifier. A unit whose outlet is no drier than the room is not earning its day.
  • Material moisture content at each mapped point, against the goal. Same points, same meter, same mode as the first visit. The trend is the proof of progress; a point that is not moving is a decision for the notes.
  • Equipment count and every change, with the reason. Units by type and asset number; anything added, removed, moved or swapped. The count billed must equal the count logged.
  • Photos of the setup, running, one wide shot per room with consistent framing.
  • Time on site and who was there. Arrival, departure and names; labor is billed from this record.

Readings taken on paper and typed up later are a reconstruction, not a record. With AIFSOP, the technician logs readings, photos and clock events on the phone straight into the job record, timestamped and located at capture.

Daily monitoring log fields
FieldWhat to recordWhy it matters to the claim
VisitDate, arrival, departure, names on siteSupports labor charges per billed day
Outside readingTemperature, RH, GPP, dew pointWhat the drying system was working against
Unaffected area readingTemperature, RH, GPP, dew pointThe building's baseline
Affected area readingTemperature, RH, GPP, dew pointThe drying environment in the work area
Dehumidifier outlet, per unitTemperature, RH, GPP, dew point, asset numberShows each unit was removing moisture
Material readingsEach mapped point: reading, meter and mode, goalThe trend toward the goal
Equipment on siteType, count, asset numbers, hours if meteredBilled equipment days must match this count
Equipment changesAdded, removed, moved or swapped, and whyExplains a changed count
PhotosThe setup that day, consistent framingConfirms placement and operation
Decisions and notesWhy the plan changedSupports demolition and extension

Demolition and removal

Removed material cannot be inspected after the fact. The photos and the reason are the only evidence there will be.

  • What was removed, with quantities. Drywall by linear feet and cut height, flooring by square feet, baseboard, insulation, cabinetry, with the material named.
  • Why. The reading that showed it would not dry in a reasonable time, or the category that made it non-restorable, tied to a reading or a photo.
  • Where. Marked on the floor plan, so the invoice quantity can be checked against the drawing.
  • Before and after photos of each area. The before shows the condition that justified removal; the after shows the open cavity and what was behind it.
  • Anything discovered. Hidden damage, growth, prior repairs. Photograph it before continuing, and write a dated note if it changes the category, class or scope.
  • Disposal. Quantity, destination and the ticket or receipt, checked against the quantities removed.

Completion

  • Final material readings at the drying goal, at every mapped point. Dated, with the goal beside each reading. This date ends the equipment charge.
  • Final photos. Every affected area, same framing as the first visit, plus the areas opened by demolition.
  • Equipment removal. Date, count and asset numbers, reconciled with the daily log.
  • Certificate of completion or customer sign-off. Signed and dated by the person who authorized the work, confirming the equipment is out.
  • Customer satisfaction. A short note or survey. No bearing on this claim, some on the next call from that adjuster.

Billing

Billing is where the file is tested. Every line item should point at a page.

  • Line items tied to the documentation. Each charge traces to a photo, a reading, a plan or a note. A line with no page behind it gets the question.
  • Equipment days matching the log. Units multiplied by days, where a day is one with a logged count and a logged reading.
  • Labor hours matching time records. Hours billed do not exceed hours recorded on site, by named people, on dated visits.
  • Demolition quantities matching the plan and the after photos.
What gets questioned and what answers it
Line item challengedWhy it gets questionedWhat answers it
Equipment days without daily readingsNothing shows the unit was there or still neededA daily log with count, outlet reading and setup photo per day
Labor without time recordsHours cannot be checked against anyone being thereClock events with names, times and location
Demolition without photosThe material is gone; nothing shows its conditionBefore and after photos, the reading or category behind it, the plan showing where
Class determination without a moisture mapClass says how much material is wet; the map is the evidenceThe first-visit moisture map with affected and unaffected readings and the dry standard
More equipment than expectedThe count looks high for the roomThe calculation with its inputs: footage, class, unit capacity
Drying that ran longExtra days look like billing, not dryingThe material trend and dated notes on what slowed it
Pre-existing damage in the scopeIt was there before the lossFirst-visit photos and notes of prior conditions

Timestamps, GPS and tamper evidence

What makes a file defensible is not its size. It is that each entry can be shown to have been created when and where it claims. Three things do that.

  • Timestamps from the device at the moment of capture. A photo re-dated in a desktop folder has no provenance, and a reading typed from a notebook is a reconstruction.
  • Location on photos and clock events. GPS on a photo places it at the property; GPS on a clock-in places the technician there for the hours billed. A GPS-verified time record turns a labor line from a claim into a fact.
  • A record that cannot be silently edited. An audit trail of who changed what and when, or a hash that proves the document is the one that was created, makes a correction visible as a correction instead of a rewrite.

None of this needs a particular tool, only a record made on site, at the time, and kept as it was made.

The report package

The adjuster's reading order is summary first, then evidence in the order the job happened. Number the pages so the invoice can reference them.

  1. Cover and job summary. Property, dates of loss, call, start and completion, claim number, category and class with the reasoning, and the scope in one paragraph.
  2. Signed work authorization.
  3. Cause and origin photos, captioned with location and date.
  4. Floor plan with affected areas, moisture map points and equipment placement.
  5. Initial moisture map and dry standard readings.
  6. Daily drying log, one page per day, with psychrometric and material readings and the equipment count.
  7. Moisture trend per point against the drying goal.
  8. Demolition record with quantities, reasons, locations and before and after photos.
  9. Equipment log: unit, asset number, date placed, date removed, days.
  10. Labor record: visits, names, time on site.
  11. Final readings and completion photos.
  12. Certificate of completion, signed.
  13. Invoice, with each line referencing the page that supports it.

AIFSOP generates this package from the job record, so the drying log holds the readings the technician took and the photos keep their original timestamps. An adjuster given access to the adjuster portal can read the record as the job runs, which tends to replace the phone call.

Build the file as the job happens

Every item here is easier to capture in the moment than to recover later, and most cannot be recovered. Nothing happens on site without a record of it made on site. For the readings themselves, see psychrometrics and drying logs.